Blackland TX
What is being sited here
Energy and data-center projects on record in Navarro and Hill counties. Every figure below is followed by the record it came from and the date that record was read. This page reports what public records say about these projects. It takes no position on any of them.
Most of what follows holds a position in ERCOT's interconnection queue. A queue position is a request to connect to the grid: it is not a permit, and it is not a construction start. Each project's stage is given in ERCOT's own words rather than summarized, and ERCOT's own abbreviations are: SS, the security screening study; FIS, the full interconnection study; IA, the interconnection agreement; POI, the point of interconnection; COD, the commercial operation date.
Three separate public records were searched, because no one of them holds everything: the ERCOT generation queue, the Commissioners Court records of both counties, and municipal records. A data center draws power rather than generating it, so it does not enter the generation queue at all — unless it builds its own power plant, in which case the plant enters the queue under the data center company's name.
Data centers, and the generation built for them
A data center is electrical load, not generation. Where one builds its own power plant, that plant holds the queue position and the data center company is named as the interconnecting entity.
- County
- Hill
- Technology
- Gas, combined cycle
- Capacity
- 1,400 MW
- Interconnecting entity
- Bullock Data Center, LLC
- Developer
- NextEra Energy Resources
- Point of interconnection
- BULLOCK 345 KV STATION (Bus# 68096)
- Status
- SS Completed, FIS Started, No IA
- Projected completion
- 1 July 2032
- Queue number
- 33INR0005
No TCEQ registration or air permit, no Chapter 312 abatement, no reinvestment zone, no Commissioners Court item, no PUCT filing and no trade press exists for this project. For a 1,400 MW combined-cycle plant the absence of an air permit places it at an early stage.
The option tract is 64.10 acres in the J.H. Chism Survey A-129, Hill CAD parcel 135551, near Malone. The 30.660-acre exception in the underlying option is the substation — Hill CAD parcel 454776, owner Lone Star Transmission LLC, situs 3081 FM 308.
- T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
- T1Hill County OPR inst. 00174614, Vol 2435 Pg 540, recorded 29 Apr 2026 — Assignment and Assumption of Real Estate Purchase Option Contract, Hubbard Wind II, LLC to Bullock Data Center, LLC, reciting “Assignee is an affiliate of Assignor”; both signature blocks executed by Anthony Pedroni, Vice President; return-to NextEra Energy Resources, LLC, 700 Universe Blvd., Juno Beach, FL Recorded instrument (read 14 September 2026)
- T1Bullock Data Center LLC, filing number 0805905419, effective 12 Feb 2025, Delaware, active Texas SOS (read 14 September 2026)
- County
- Hill
- Technology
- Gas, combined cycle
- Capacity
- 1,400 MW
- Interconnecting entity
- Liberty Data Center I, LLC
- Developer
- NextEra Energy Resources
- Point of interconnection
- LIBERTY 345 KV STATION (Bus# 68092)
- Status
- SS Completed, FIS Started, No IA
- Projected completion
- 1 July 2032
- Queue number
- 33INR0006
No TCEQ registration or air permit, no Chapter 312 abatement, no reinvestment zone, no Commissioners Court item, no PUCT filing and no trade press exists for this project.
The option covers 357.73 acres across four Hill CAD parcels owned by 4 Dawsons Farm, LLC, on FM 339 at Wolf Creek near Mount Calm. Liberty Station is 3.7 miles south-southeast and already hosts Mercury Solar III and Mercury Storage.
- T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
- T1Hill County OPR inst. 00176826, Vol 2450 Pg 799, recorded 13 Jul 2026 — Memorandum of Real Estate Purchase Option Agreement, 4 Dawsons Farm, LLC to Liberty Data Center I, LLC, “with an address of 700 Universe Boulevard, Attn: Land Services Administration, Juno Beach, FL 33408”; signed Stuart McCurdy, Vice President Recorded instrument (read 14 September 2026)
- T1Liberty Data Center I LLC, filing number 0806367754, effective 22 Dec 2025, Delaware, active Texas SOS (read 14 September 2026)
- County
- Hill
- Technology
- Grid-tied data center load
- Capacity
- 1,235 MW claimed in trade press, not established
- Interconnecting entity
- RCM Hill, LLC
- Status
- In litigation
The project's location is not established. The complaint states the site is unincorporated with no extraterritorial jurisdiction; no release petition exists in Hillsboro's own records; and the coordinates carried in trade press resolve to Katy Lake itself on the Hill CAD parcel layer.
The complaint withholds the four landowners' names and any legal description. They are named only in sealed exhibits.
RCM Hill, LLC has no recorded instrument of any kind in the Hill County Clerk index under any name.
- T1Complaint in 6:26-cv-00340, free on RECAP — four contracts with four landowners between Apr 2025 and Jan 2026, 800+ acres, $80M+, about $100,000 per acre against the 2025 Hill CAD agricultural appraisal of $7,100 per acre, $1M in pursuit costs over 16 months, and the full interconnection chain through PUCT Project No. 58481 Federal court filing (read 14 September 2026)
- T1Hill County moratorium Order 2026-5154 adopted 3–2 on 12 May 2026; rescinded unanimously 4 Jun 2026 by Order 2026-5202; checklist Order 2026-5204; $100,000 authorised 30 Jun 2026 by Order 2026-5262 Commissioners Court (read 14 September 2026)
- County
- Hill
- Technology
- Data center load
- Capacity
- No capacity figure exists in the primary record
- Interconnecting entity
- Provident-GRH Hillsboro, LP
- Developer
- Provident Realty Advisors Inc.
- Status
- Contract not closed; zoning not approved
Water is the stated constraint and the City said so on the record: a water-cooled design at 3.6 million gallons per day peak was rejected, an air-cooled design at 1.56 million gallons per day is under discussion, and no will-serve letter has issued.
- T1City of Hillsboro's own data center transparency page — about 293.84 acres of Hillsboro EDC land inside the city limits in the John E. Ross A-750 and Ewen Cameron A-131 surveys; contract in place since Sep 2024, running through Nov 2026, amended twice; Planning and Zoning considered a text amendment adding “Data Center” to the permitted use table on 11 May and 27 Jul 2026 with no council adoption through the 15 Sep agenda Municipal record (read 14 September 2026)
- T1Hillsboro Municipal Management District No. 1, $81M estimated district cost; city consent conditional under Resolution R2025-03-16 Municipal record (read 14 September 2026)
- County
- Navarro
- Technology
- Bitcoin mining and data center load
- Capacity
- 400 MW operational
- Interconnecting entity
- Riot Corsicana, LLC
- Developer
- Riot Platforms, Inc.
- Status
- Operational
- Projected completion
- Substation energized April 2024
No amendment for the announced expansion to approximately 1 GW appears in Navarro County minutes.
- T1Riot Platforms FY2025 Form 10-K, accession 0001104659-26-022322, and Q2 2026 Form 10-Q, accession 0001104659-26-093448 — 265.71 acres in the J. Taylor Survey Block 233 Abstract 11, substation energized April 2024, 400 MW operational at 31 Dec 2024 and still 400 MW at 30 Jun 2026, approximately 1 GW planned, Oncor delivery SEC filing (read 14 September 2026)
- T1Navarro County tax abatement approved 3–2 on 15 Oct 2024, Reinvestment Zone 24-102, 50% for 10 years, $640M, 140 jobs; the document states 920 MW of demand. An earlier attempt died for want of a second on 11 Mar 2024. Commissioners Court (read 14 September 2026)
Navarro County
Generation projects holding an active position in the ERCOT interconnection queue.
- County
- Navarro
- Technology
- Solar, photovoltaic
- Capacity
- 150.48 MW
- Interconnecting entity
- Armadillo Solar Center, LLC
- Developer
- AES Clean Energy
- Point of interconnection
- 3387 Revolution 138kV
- Status
- SS Completed, FIS Completed, IA
- Projected completion
- 4 December 2026
- Queue number
- 21INR0421
- T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
- T1EIA plant record 64349, Armadillo Solar Center, planned EIA (read 14 September 2026)
- T1AES Clean Energy established from officer records Corporate record (read 14 September 2026)
- County
- Navarro
- Technology
- Wind, wind turbine
- Capacity
- 180 MW
- Interconnecting entity
- Bluebonnet Prairie Wind, LLC
- Developer
- Leeward Renewable Energy
- Point of interconnection
- Tap 138kV 200 CHATFIELD - 3454 MONTFTSS__8
- Status
- SS Completed, FIS Started, IA
- Projected completion
- 15 July 2028
- Queue number
- 25INR0247
- T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
- T1EIA Form 860M, July 2026 — Plant 68082, Bluebonnet Prairie Wind, Leeward Renewable Energy, Navarro County, 170 MW, under construction EIA Form 860M (read 14 September 2026)
- County
- Navarro
- Technology
- Wind, wind turbine
- Capacity
- 299.2 MW
- Interconnecting entity
- Limestone Wind Project, LLC
- Developer
- Limestone Wind Project, LLC
- Point of interconnection
- 345kV 3386 Outlaw Switch
- Status
- SS Completed, FIS Completed, IA
- Projected completion
- 31 October 2026
- Queue number
- 21INR0324
- T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
- T1Navarro County tax abatement for Limestone Wind denied 1–3, 2022 Commissioners Court (read 14 September 2026)
- County
- Navarro
- Technology
- Other, battery
- Capacity
- 150.52 MW
- Interconnecting entity
- Cape Rich BESS
- Developer
- Navitas Energy
- Point of interconnection
- 3387 Revolution Switch 138kV
- Status
- SS Completed, FIS Completed, IA
- Projected completion
- 18 April 2030
- Queue number
- 26INR0180
- T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
- T1Navitas Energy established from officer records Corporate record (read 14 September 2026)
- County
- Navarro
- Technology
- Solar, photovoltaic
- Capacity
- 125.84 MW
- Interconnecting entity
- Orca Falls Solar, LLC
- Point of interconnection
- Tap 138kV 3472 BRIAR_CRK_8 – 3467 POWELL1_8
- Status
- SS Completed, FIS Started, IA
- Projected completion
- 30 September 2027
- Queue number
- 26INR0130
- T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
- T1Navarro County — Orca Falls Solar rezoning denied Feb 2026; road crossings approved Aug 2026 Commissioners Court (read 14 September 2026)
- County
- Navarro
- Technology
- Other, battery
- Capacity
- Filed as 0 MW in the queue
- Interconnecting entity
- Orca Falls Solar, LLC
- Point of interconnection
- Tap 138kV 3472 BRIAR_CRK_8 – 3467 POWELL1_8
- Status
- SS Completed, FIS Started, IA
- Projected completion
- 30 September 2027
- Queue number
- 26INR0131
- T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
- T1Navarro County — Orca Falls Solar rezoning denied Feb 2026; road crossings approved Aug 2026 Commissioners Court (read 14 September 2026)
- County
- Navarro
- Technology
- Solar, photovoltaic
- Capacity
- 203.5 MW
- Interconnecting entity
- Glasgow Solar LLC
- Developer
- Belltown Power
- Point of interconnection
- Tap 345kV #2466 Big Onion - #68091 Navarro
- Status
- SS Completed, FIS Started, IA
- Projected completion
- 16 March 2028
- Queue number
- 24INR0206
- T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
- T1Belltown Power established from officer records Corporate record (read 14 September 2026)
- County
- Navarro
- Technology
- Other, battery
- Capacity
- 101 MW
- Interconnecting entity
- Glasgow Solar LLC
- Developer
- Belltown Power
- Point of interconnection
- Tap 345kV #2466 Big Onion - #68091 Navarro
- Status
- SS Completed, FIS Started, IA
- Projected completion
- 16 March 2028
- Queue number
- 24INR0207
- T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
- T1Belltown Power established from officer records Corporate record (read 14 September 2026)
- County
- Navarro
- Technology
- Solar, photovoltaic
- Capacity
- 221.36 MW
- Interconnecting entity
- GoodAlta Power Center LLC
- Point of interconnection
- tap 138kV 3127 Trinidad - 212 Winkler
- Status
- SS Completed, FIS Completed, No IA
- Projected completion
- 20 September 2027
- Queue number
- 23INR0171
- T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
- T1Navarro County — GoodAlta Power Center LLC tax abatement failed for want of a second, 2021 Commissioners Court (read 14 September 2026)
- County
- Navarro
- Technology
- Solar, photovoltaic
- Capacity
- 81.59 MW
- Interconnecting entity
- Hector Solar, LLC
- Developer
- Samsung C&T Renewables
- Point of interconnection
- Haney (213) - Hubbard_8 (3515) 138kV Line
- Status
- SS Completed, FIS Started, No IA
- Projected completion
- 8 October 2028
- Queue number
- 25INR0220
- T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
- T1Samsung C&T Renewables established from officer records; absent from Navarro County records entirely Corporate record (read 14 September 2026)
- County
- Navarro
- Technology
- Other, battery
- Capacity
- 42.69 MW
- Interconnecting entity
- Hector Solar, LLC
- Developer
- Samsung C&T Renewables
- Point of interconnection
- Haney (213) - Hubbard_8 (3515) 138kV Line
- Status
- SS Completed, FIS Started, No IA
- Projected completion
- 8 October 2028
- Queue number
- 25INR0221
- T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
- T1Samsung C&T Renewables established from officer records; absent from Navarro County records entirely Corporate record (read 14 September 2026)
- County
- Navarro
- Technology
- Solar, photovoltaic
- Capacity
- 101.5 MW
- Interconnecting entity
- Kennedy Bypass Solar LLC
- Point of interconnection
- Tap 345kV 68040 Kopprl Capacitor Yard - 68091 Navarro
- Status
- SS Completed, FIS Started, No IA
- Projected completion
- 31 December 2028
- Queue number
- 24INR0256
Kennedy Bypass Solar LLC has no Texas corporate registration. The project exists as a queue position and nothing else on record.
- T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
- T1Kennedy Bypass Solar LLC has no Texas corporate registration of any kind — checked against franchise tax, Secretary of State, EIA, TCEQ, Navarro County minutes, Chapter 312 and the Comptroller JETI registry. The project exists only as a queue position. Documented negative (read 14 September 2026)
- County
- Navarro
- Technology
- Other, battery
- Capacity
- 25.3 MW
- Interconnecting entity
- Kennedy Bypass Solar LLC
- Point of interconnection
- Tap 345kV 68040 Kopprl Capacitor Yard - 68091 Navarro
- Status
- SS Completed, FIS Started, No IA
- Projected completion
- 31 December 2028
- Queue number
- 24INR0391
Kennedy Bypass Solar LLC has no Texas corporate registration. The project exists as a queue position and nothing else on record.
- T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
- T1Kennedy Bypass Solar LLC has no Texas corporate registration of any kind — checked against franchise tax, Secretary of State, EIA, TCEQ, Navarro County minutes, Chapter 312 and the Comptroller JETI registry. The project exists only as a queue position. Documented negative (read 14 September 2026)
- County
- Navarro
- Technology
- Solar, photovoltaic
- Capacity
- 100.43 MW
- Interconnecting entity
- Main Horn Solar LLC
- Developer
- OCI Energy
- Point of interconnection
- 3387 Revolution 138 KV
- Status
- SS Completed, FIS Started, No IA
- Projected completion
- 17 September 2029
- Queue number
- 28INR0467
- T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
- T1EIA Form 860M, July 2026 — Plant 69636, Main Horn Solar, 100 MW, planned EIA Form 860M (read 14 September 2026)
- County
- Navarro
- Technology
- Solar, photovoltaic
- Capacity
- 251.3 MW
- Interconnecting entity
- Oak Valley Solar LLC
- Developer
- Alpin Solar SA, Brașov, Romania (via Alpin Holding LLC, Canyon, Texas)
- Point of interconnection
- 68091 (Navarro) (345)
- Status
- SS Completed, FIS Started, No IA
- Projected completion
- 28 September 2029
- Queue number
- 28INR0335
- T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
- T1Alpin Holding LLC of Canyon, Texas, parent Alpin Solar SA of Brașov, Romania, from officer records. Appears in no county record, no federal inventory and no trade press. Corporate record (read 14 September 2026)
- County
- Navarro
- Technology
- Solar, photovoltaic
- Capacity
- 101.89 MW
- Interconnecting entity
- Pisgah Ridge Solar 2, LLC
- Developer
- Duke Energy
- Point of interconnection
- Tap 345kV 68091 Navarro - 46020 Limestone
- Status
- SS Completed, FIS Started, No IA
- Projected completion
- 31 March 2029
- Queue number
- 24INR0086
- T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
- T1Navarro County Reinvestment Zone 20-102, Pisgah Ridge Solar, 3,688 acres, 200 MW minimum Commissioners Court (read 14 September 2026)
- County
- Navarro
- Technology
- Solar, photovoltaic
- Capacity
- 148.87 MW
- Interconnecting entity
- Karol Solar VI
- Developer
- Solea Power Corp. (Houston and Madrid)
- Point of interconnection
- Tap 138 KV 3456 CORSWEST1_8 - 3457 CORS_MOBT_8
- Status
- SS Completed, FIS Started, No IA
- Projected completion
- 6 April 2029
- Queue number
- 28INR0182
- T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
- T1Karol Solar VI, parent Solea Power Corp. of Houston and Madrid, from officer records Corporate record (read 14 September 2026)
- County
- Navarro
- Technology
- Solar, photovoltaic
- Capacity
- 105.85 MW
- Interconnecting entity
- Karol Solar IV
- Developer
- Solea Power Corp. (Houston and Madrid)
- Point of interconnection
- Tap 345 KV 68091 NAVARRO - 3381 BIGBRNW_5 Ckt 2
- Status
- SS Completed, FIS Completed, No IA
- Projected completion
- 20 September 2028
- Queue number
- 26INR0228
- T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
- T1Karol Solar IV, parent Solea Power Corp. of Houston and Madrid, from officer records Corporate record (read 14 September 2026)
- County
- Navarro
- Technology
- Solar, photovoltaic
- Capacity
- 356.6 MW
- Interconnecting entity
- BDPU SOLAR TORMES LLC
- Developer
- Matrix Renewables (TPG Rise Climate)
- Point of interconnection
- tap 345kV 1906 Venus - 68091 Navarro
- Status
- SS Completed, FIS Completed, IA
- Projected completion
- 31 March 2027
- Queue number
- 22INR0437
- T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
- T2Matrix Renewables press release and project page, 28 May 2026 — groundbreaking 19 May 2026, 457 MWdc, approximately $750M, EPC contractor SOLV Energy, site about two miles southeast of Barry, west of Corsicana Developer publication (read 14 September 2026)
- County
- Navarro
- Technology
- Solar, photovoltaic
- Capacity
- 146.08 MW
- Interconnecting entity
- Greenalia Solar Power Wensowitch LLC
- Developer
- Greenalia S.A. (Spain)
- Point of interconnection
- Tapping 138 kV line Telico (192) to Montfort Switch (3454)
- Status
- SS Completed, FIS Completed, No IA
- Projected completion
- 18 September 2028
- Queue number
- 24INR0205
- T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
- T1EIA Form 860M, July 2026 — Plant 67567, Wensowitch Solar Park, 145.6 MW EIA Form 860M (read 14 September 2026)
- County
- Navarro
- Technology
- Other, battery
- Capacity
- 359.1 MW
- Interconnecting entity
- Wildflower Storage LLC
- Developer
- Matrix Renewables (TPG Rise Climate)
- Point of interconnection
- Drane switch #3295
- Status
- SS Completed, FIS Started, No IA
- Projected completion
- 30 September 2028
- Queue number
- 28INR0292
- T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
- T1Matrix Renewables (TPG Rise Climate) established from officer records Corporate record (read 14 September 2026)
- County
- Navarro
- Technology
- Wind, wind turbine
- Capacity
- 262 MW
- Interconnecting entity
- Yellow Cat Wind LLC
- Developer
- RWE
- Point of interconnection
- Tap 345kV 1906 Venus - 68091 Navarro
- Status
- SS Completed, FIS Completed, IA
- Projected completion
- 5 March 2027
- Queue number
- 25INR0018
RWE's own project page places part of this project in Ellis County, which is outside the two counties this page covers.
- T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
- T2RWE project page — developer confirmed, “over 67,250 homes” powered, 30-year landowner lease framing, and a stated capacity of 270 MW against the queue's 262 MW. The same page places the project in Navarro, Ellis and Hill counties. Developer publication (read 14 September 2026)
Hill County
Generation projects holding an active position in the ERCOT interconnection queue.
- County
- Hill
- Technology
- Wind, wind turbine
- Capacity
- 297.4 MW
- Interconnecting entity
- Aquilla Lake 3 Wind
- Developer
- NextEra Energy Resources (via Hubbard Wind II, LLC)
- Point of interconnection
- tap 345 kV 68040 Kopperl to 68091 Navarro
- Status
- SS Completed, FIS Completed, IA
- Projected completion
- 20 November 2026
- Queue number
- 22INR0499
- T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
- T1PUC Docket 57836 — Lone Star Transmission CCN amendment filed 11 Apr 2025 for the Bullock Station to Aquilla Lake III 345-kV line, naming Hubbard Wind II, LLC PUCT filing (read 14 September 2026)
- County
- Hill
- Technology
- Other, battery
- Capacity
- 306.26 MW
- Interconnecting entity
- ACTX BESS Project LLC
- Developer
- Primergy Solar (Quinbrook Infrastructure Partners)
- Point of interconnection
- 68090 SAM SW 345kV
- Status
- SS Completed, FIS Started, IA
- Projected completion
- 1 April 2028
- Queue number
- 25INR0046
Primergy's franchise mailing address has moved to Scottsdale, Arizona. The parent should be re-checked before this row is relied on.
- T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
- T1Primergy Solar (Quinbrook Infrastructure Partners) established from officer records Corporate record (read 14 September 2026)
- County
- Hill
- Technology
- Solar, photovoltaic
- Capacity
- 405.7 MW
- Interconnecting entity
- Hill Solar I, LLC
- Developer
- OCI Energy
- Point of interconnection
- tap 345kV 68090 Sam Switch - 1907 Venus
- Status
- SS Completed, FIS Completed, IA
- Projected completion
- 31 July 2026
- Queue number
- 24INR0023
- T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
- T1Hill County road use agreement with Hill Solar I, LLC, 25 Apr 2023 Commissioners Court (read 14 September 2026)
- County
- Hill
- Technology
- Solar, photovoltaic
- Capacity
- 201.4 MW
- Interconnecting entity
- Hill Solar II, LLC
- Developer
- OCI Energy
- Point of interconnection
- Tap 345kV 68090 Sam Switch – 3389 Fort Smith
- Status
- SS Completed, FIS Completed, IA
- Projected completion
- 1 October 2026
- Queue number
- 25INR0166
- T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
- T1Hill County road use agreement with Hill Solar II, 27 Dec 2023 Commissioners Court (read 14 September 2026)
- County
- Hill
- Technology
- Solar, photovoltaic
- Capacity
- 70.75 MW
- Interconnecting entity
- Hill PV, LLC
- Developer
- OCI Energy
- Point of interconnection
- Tap 69kV 3532 Itasca - 3523 Hillsboro
- Status
- SS Completed, FIS Started, No IA
- Projected completion
- 9 April 2028
- Queue number
- 26INR0313
- T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
- T1Hill County Reinvestment Zone 20 for Hill PV, LLC, 22 Oct 2024, and tax abatement 10 Dec 2024 Commissioners Court (read 14 September 2026)
- County
- Hill
- Technology
- Solar, photovoltaic
- Capacity
- 182 MW
- Interconnecting entity
- High Noon Solar Project, LLC
- Developer
- Enel Green Power North America
- Point of interconnection
- Tap 138kV 445 Yates - 444 Covington
- Status
- SS Completed, FIS Started, IA
- Projected completion
- 9 May 2028
- Queue number
- 24INR0124
- T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
- T1Enel Green Power North America established from officer records Corporate record (read 14 September 2026)
- County
- Hill
- Technology
- Other, battery
- Capacity
- 94 MW
- Interconnecting entity
- High Noon Solar Project, LLC
- Developer
- Enel Green Power North America
- Point of interconnection
- Tap 138kV 445 Yates - 444 Covington
- Status
- SS Completed, FIS Started, IA
- Projected completion
- 9 May 2028
- Queue number
- 24INR0126
- T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
- T1Enel Green Power North America established from officer records Corporate record (read 14 September 2026)
- County
- Hill
- Technology
- Gas, combined cycle
- Capacity
- 1,253 MW
- Interconnecting entity
- NRG Prairie Energy Center LLC
- Point of interconnection
- Tap #1907 Venus Switch – #3389 Fort Smith Switch 345 kV
- Status
- SS Completed, FIS Started, No IA
- Projected completion
- 31 December 2030
- Queue number
- 29INR0158
Recorded on 13 Sep 2026 as a project appearing on no tracker. It is in the ERCOT generation queue, and this page corrects that.
- T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
- T1TCEQ air permit application 183570 / PSDTX1706 / GHGPSDTX272, received 31 Mar 2026, expedited — power generation at CR 4419 / FM 66 southeast of Grandview; filed with the Hill County Judge on the county projects page TCEQ (read 14 September 2026)
- County
- Hill
- Technology
- Other, battery
- Capacity
- 201.6 MW
- Interconnecting entity
- Hillsboro Solar Project LLC
- Developer
- OCI Energy
- Point of interconnection
- tap 345kV 1907 Venus - 68090 Sam Sw
- Status
- SS Completed, FIS Completed, IA
- Projected completion
- 31 December 2028
- Queue number
- 25INR0233
- T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
- T1Hill County Reinvestment Zone 012, OCI Hillsboro Solar, with assignee Hillsboro BESS Project LLC Commissioners Court (read 14 September 2026)
- County
- Hill
- Technology
- Solar, photovoltaic
- Capacity
- 203.1 MW
- Interconnecting entity
- Hillsboro Solar Project LLC
- Developer
- OCI Energy
- Point of interconnection
- tap 345kV 1907 Venus - 68090 Sam Sw
- Status
- SS Completed, FIS Completed, IA
- Projected completion
- 31 December 2027
- Queue number
- 25INR0229
- T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
- T1Hill County Reinvestment Zone 012, OCI Hillsboro Solar Commissioners Court (read 14 September 2026)
- County
- Hill
- Technology
- Solar, photovoltaic
- Capacity
- 84.99 MW
- Interconnecting entity
- Gransolar Texas Ten, LLC
- Developer
- Gransolar
- Point of interconnection
- tap 138kV 213 Haney - 3515 Hubbard
- Status
- SS Completed, FIS Started, IA
- Projected completion
- 25 August 2027
- Queue number
- 24INR0106
- T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
- T1Hill County Reinvestment Zone 009, Gransolar Texas Ten, 83.6 MWac as stated in the county record Commissioners Court (read 14 September 2026)
- County
- Hill
- Technology
- Other, battery
- Capacity
- 514 MW
- Interconnecting entity
- Seven Angels Infrastructure LLC
- Developer
- Polaris Infrastructure Development LLC, originated by Macro Grid Solutions LLC (both Denver)
- Point of interconnection
- 68090 Sam Switch Bus 345kV
- Status
- SS Completed, FIS Started, No IA
- Projected completion
- 31 December 2028
- Queue number
- 28INR0472
- T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
- T1Polaris Infrastructure Development LLC, originated by Macro Grid Solutions LLC, both of Denver, from officer records Corporate record (read 14 September 2026)
- County
- Hill
- Technology
- Other, battery
- Capacity
- 514 MW
- Interconnecting entity
- Seven Angels Infrastructure LLC
- Developer
- Polaris Infrastructure Development LLC, originated by Macro Grid Solutions LLC (both Denver)
- Point of interconnection
- 68090 Sam Switch Bus 345kV
- Status
- SS Completed, FIS Started, No IA
- Projected completion
- 31 December 2028
- Queue number
- 28INR0473
- T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
- T1Polaris Infrastructure Development LLC, originated by Macro Grid Solutions LLC, both of Denver, from officer records Corporate record (read 14 September 2026)
- County
- Hill
- Technology
- Solar, photovoltaic
- Capacity
- 110.89 MW
- Interconnecting entity
- Three W Solar LLC
- Point of interconnection
- tap 138kV 3522 Hillboro1_8 - 237 Blanton CKT 1
- Status
- SS Completed, FIS Completed, IA
- Projected completion
- 4 September 2026
- Queue number
- 25INR0055
- T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
- T1Hill County Reinvestment Zone 013, Three W Solar, with four named landowners publicly noticed (Westmoreland ×2, Swann, Williams) Commissioners Court (read 14 September 2026)
- County
- Hill
- Technology
- Other, battery
- Capacity
- 135.18 MW
- Interconnecting entity
- Gransolar Texas Eleven LLC
- Developer
- Gransolar
- Point of interconnection
- Chatt(234) - Pecan Street (3352) 138kV
- Status
- SS Completed, FIS Completed, IA
- Projected completion
- 15 September 2027
- Queue number
- 25INR0122
- T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
- T1Hill County Reinvestment Zone 014, Gransolar Texas Eleven, 135.12 MWac BESS as stated in the county record Commissioners Court (read 14 September 2026)
6 queue positions in these counties are carried by ERCOT as inactive. An inactive position is not a project and is not listed here.
Queue data: ERCOT GIS Report for August 2026, posted 1 September 2026, read 14 September 2026. Second sources are named against each project. Where two records give different figures for the same project, both are shown with their sources and neither is picked. ERCOT publishes the report for planning purposes only, states that its data comes from the interconnecting entities and transmission service providers themselves, and cautions that it may contain errors or be out of date depending on when it was entered. Compiled by Blackland TX.