Energy and data-center projects

Energy and data-center projects on record in Navarro and Hill counties. Each one has its own page with its figures and their sources. This page takes no position on any of them.
Where they are
9 of the 43 projects below are on the map. The other 34 are places in the grid queue with no public location.
The map is wider than the screen. Drag it sideways.
All 43 projects, grouped below by county.
Jump to: Data centers · Navarro County · Hill County
Data centers, and the generation built for them
A data center uses power rather than making it. Where one builds its own power plant, the plant is listed under the data center company's name.
Bullock GasHill County · Gas, combined cycle · 1,400 MW · completion projected 2032Liberty Thermal Energy CenterHill County · Gas, combined cycle · 1,400 MW · completion projected 2032Nexus Data Centers, HubbardHill County · Behind-the-meter gas generationProject Aquila (RCM Hill)Hill County · Grid-tied data center loadProvident Data Centers, HillsboroHill County · Data center loadRiot Platforms CorsicanaNavarro County · Bitcoin mining and data center loadHill County
Power projects with an active place in the ERCOT grid queue.
Aquilla Lake 3 WindWind · 297.4 MW · completion projected 2026Blue Skies BESSBattery storage · 306.26 MW · completion projected 2028Compadre SolarSolar · 405.7 MW · completion projected 2026Compadre Solar IISolar · 201.4 MW · completion projected 2026Edens SolarSolar · 70.75 MW · completion projected 2028High Noon SolarSolar · 182 MW · completion projected 2028High Noon StorageBattery storage · 94 MW · completion projected 2028NRG Prairie Energy CenterGas, combined cycle · 1,253 MW · completion projected 2030OCI Cobb Creek ESSBattery storage · 201.6 MW · completion projected 2028OCI Cobb Creek SolarSolar · 203.1 MW · completion projected 2027Payne BattlecreekSolar · 84.99 MW · completion projected 2027Seven Angels Energy Storage IBattery storage · 514 MW · completion projected 2028Seven Angels Energy Storage IIBattery storage · 514 MW · completion projected 2028Three W SolarSolar · 110.89 MW · completion projected 2026Vial BESSBattery storage · 135.18 MW · completion projected 2027Queue data: ERCOT GIS Report, August 2026 (posted 1 September 2026, read 30 September 2026). Compiled by Blackland TX. Corrections: [email protected].