Blackland TX

What is being sited here

Energy and data-center projects on record in Navarro and Hill counties. Every figure below is followed by the record it came from and the date that record was read. This page reports what public records say about these projects. It takes no position on any of them.

Most of what follows holds a position in ERCOT's interconnection queue. A queue position is a request to connect to the grid: it is not a permit, and it is not a construction start. Each project's stage is given in ERCOT's own words rather than summarized, and ERCOT's own abbreviations are: SS, the security screening study; FIS, the full interconnection study; IA, the interconnection agreement; POI, the point of interconnection; COD, the commercial operation date.

Three separate public records were searched, because no one of them holds everything: the ERCOT generation queue, the Commissioners Court records of both counties, and municipal records. A data center draws power rather than generating it, so it does not enter the generation queue at all — unless it builds its own power plant, in which case the plant enters the queue under the data center company's name.

Data centers, and the generation built for them

A data center is electrical load, not generation. Where one builds its own power plant, that plant holds the queue position and the data center company is named as the interconnecting entity.

Bullock Gas
County
Hill
Technology
Gas, combined cycle
Capacity
1,400 MW
Interconnecting entity
Bullock Data Center, LLC
Developer
NextEra Energy Resources
Point of interconnection
BULLOCK 345 KV STATION (Bus# 68096)
Status
SS Completed, FIS Started, No IA
Projected completion
1 July 2032
Queue number
33INR0005

No TCEQ registration or air permit, no Chapter 312 abatement, no reinvestment zone, no Commissioners Court item, no PUCT filing and no trade press exists for this project. For a 1,400 MW combined-cycle plant the absence of an air permit places it at an early stage.

The option tract is 64.10 acres in the J.H. Chism Survey A-129, Hill CAD parcel 135551, near Malone. The 30.660-acre exception in the underlying option is the substation — Hill CAD parcel 454776, owner Lone Star Transmission LLC, situs 3081 FM 308.

  • T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
  • T1Hill County OPR inst. 00174614, Vol 2435 Pg 540, recorded 29 Apr 2026 — Assignment and Assumption of Real Estate Purchase Option Contract, Hubbard Wind II, LLC to Bullock Data Center, LLC, reciting “Assignee is an affiliate of Assignor”; both signature blocks executed by Anthony Pedroni, Vice President; return-to NextEra Energy Resources, LLC, 700 Universe Blvd., Juno Beach, FL Recorded instrument (read 14 September 2026)
  • T1Bullock Data Center LLC, filing number 0805905419, effective 12 Feb 2025, Delaware, active Texas SOS (read 14 September 2026)
Liberty Thermal Energy Center
County
Hill
Technology
Gas, combined cycle
Capacity
1,400 MW
Interconnecting entity
Liberty Data Center I, LLC
Developer
NextEra Energy Resources
Point of interconnection
LIBERTY 345 KV STATION (Bus# 68092)
Status
SS Completed, FIS Started, No IA
Projected completion
1 July 2032
Queue number
33INR0006

No TCEQ registration or air permit, no Chapter 312 abatement, no reinvestment zone, no Commissioners Court item, no PUCT filing and no trade press exists for this project.

The option covers 357.73 acres across four Hill CAD parcels owned by 4 Dawsons Farm, LLC, on FM 339 at Wolf Creek near Mount Calm. Liberty Station is 3.7 miles south-southeast and already hosts Mercury Solar III and Mercury Storage.

  • T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
  • T1Hill County OPR inst. 00176826, Vol 2450 Pg 799, recorded 13 Jul 2026 — Memorandum of Real Estate Purchase Option Agreement, 4 Dawsons Farm, LLC to Liberty Data Center I, LLC, “with an address of 700 Universe Boulevard, Attn: Land Services Administration, Juno Beach, FL 33408”; signed Stuart McCurdy, Vice President Recorded instrument (read 14 September 2026)
  • T1Liberty Data Center I LLC, filing number 0806367754, effective 22 Dec 2025, Delaware, active Texas SOS (read 14 September 2026)
Project Aquila (RCM Hill)
County
Hill
Technology
Grid-tied data center load
Capacity
1,235 MW claimed in trade press, not established
Interconnecting entity
RCM Hill, LLC
Status
In litigation

The project's location is not established. The complaint states the site is unincorporated with no extraterritorial jurisdiction; no release petition exists in Hillsboro's own records; and the coordinates carried in trade press resolve to Katy Lake itself on the Hill CAD parcel layer.

The complaint withholds the four landowners' names and any legal description. They are named only in sealed exhibits.

RCM Hill, LLC has no recorded instrument of any kind in the Hill County Clerk index under any name.

  • T1Complaint in 6:26-cv-00340, free on RECAP — four contracts with four landowners between Apr 2025 and Jan 2026, 800+ acres, $80M+, about $100,000 per acre against the 2025 Hill CAD agricultural appraisal of $7,100 per acre, $1M in pursuit costs over 16 months, and the full interconnection chain through PUCT Project No. 58481 Federal court filing (read 14 September 2026)
  • T1Hill County moratorium Order 2026-5154 adopted 3–2 on 12 May 2026; rescinded unanimously 4 Jun 2026 by Order 2026-5202; checklist Order 2026-5204; $100,000 authorised 30 Jun 2026 by Order 2026-5262 Commissioners Court (read 14 September 2026)
Provident Data Centers, Hillsboro
County
Hill
Technology
Data center load
Capacity
No capacity figure exists in the primary record
Interconnecting entity
Provident-GRH Hillsboro, LP
Developer
Provident Realty Advisors Inc.
Status
Contract not closed; zoning not approved

Water is the stated constraint and the City said so on the record: a water-cooled design at 3.6 million gallons per day peak was rejected, an air-cooled design at 1.56 million gallons per day is under discussion, and no will-serve letter has issued.

  • T1City of Hillsboro's own data center transparency page — about 293.84 acres of Hillsboro EDC land inside the city limits in the John E. Ross A-750 and Ewen Cameron A-131 surveys; contract in place since Sep 2024, running through Nov 2026, amended twice; Planning and Zoning considered a text amendment adding “Data Center” to the permitted use table on 11 May and 27 Jul 2026 with no council adoption through the 15 Sep agenda Municipal record (read 14 September 2026)
  • T1Hillsboro Municipal Management District No. 1, $81M estimated district cost; city consent conditional under Resolution R2025-03-16 Municipal record (read 14 September 2026)
Riot Platforms Corsicana
County
Navarro
Technology
Bitcoin mining and data center load
Capacity
400 MW operational
Interconnecting entity
Riot Corsicana, LLC
Developer
Riot Platforms, Inc.
Status
Operational
Projected completion
Substation energized April 2024

No amendment for the announced expansion to approximately 1 GW appears in Navarro County minutes.

  • T1Riot Platforms FY2025 Form 10-K, accession 0001104659-26-022322, and Q2 2026 Form 10-Q, accession 0001104659-26-093448 — 265.71 acres in the J. Taylor Survey Block 233 Abstract 11, substation energized April 2024, 400 MW operational at 31 Dec 2024 and still 400 MW at 30 Jun 2026, approximately 1 GW planned, Oncor delivery SEC filing (read 14 September 2026)
  • T1Navarro County tax abatement approved 3–2 on 15 Oct 2024, Reinvestment Zone 24-102, 50% for 10 years, $640M, 140 jobs; the document states 920 MW of demand. An earlier attempt died for want of a second on 11 Mar 2024. Commissioners Court (read 14 September 2026)

Navarro County

Generation projects holding an active position in the ERCOT interconnection queue.

Armadillo Solar
County
Navarro
Technology
Solar, photovoltaic
Capacity
150.48 MW
Interconnecting entity
Armadillo Solar Center, LLC
Developer
AES Clean Energy
Point of interconnection
3387 Revolution 138kV
Status
SS Completed, FIS Completed, IA
Projected completion
4 December 2026
Queue number
21INR0421
  • T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
  • T1EIA plant record 64349, Armadillo Solar Center, planned EIA (read 14 September 2026)
  • T1AES Clean Energy established from officer records Corporate record (read 14 September 2026)
Bluebonnet Prairie Wind
County
Navarro
Technology
Wind, wind turbine
Capacity
180 MW — EIA Form 860M gives 170 MW; the ERCOT queue gives 180 MW.
Interconnecting entity
Bluebonnet Prairie Wind, LLC
Developer
Leeward Renewable Energy
Point of interconnection
Tap 138kV 200 CHATFIELD - 3454 MONTFTSS__8
Status
SS Completed, FIS Started, IA
Projected completion
15 July 2028
Queue number
25INR0247
  • T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
  • T1EIA Form 860M, July 2026 — Plant 68082, Bluebonnet Prairie Wind, Leeward Renewable Energy, Navarro County, 170 MW, under construction EIA Form 860M (read 14 September 2026)
Board Creek Wind
County
Navarro
Technology
Wind, wind turbine
Capacity
299.2 MW
Interconnecting entity
Limestone Wind Project, LLC
Developer
Limestone Wind Project, LLC
Point of interconnection
345kV 3386 Outlaw Switch
Status
SS Completed, FIS Completed, IA
Projected completion
31 October 2026
Queue number
21INR0324
  • T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
  • T1Navarro County tax abatement for Limestone Wind denied 1–3, 2022 Commissioners Court (read 14 September 2026)
Cape Rich BESS
County
Navarro
Technology
Other, battery
Capacity
150.52 MW
Interconnecting entity
Cape Rich BESS
Developer
Navitas Energy
Point of interconnection
3387 Revolution Switch 138kV
Status
SS Completed, FIS Completed, IA
Projected completion
18 April 2030
Queue number
26INR0180
  • T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
  • T1Navitas Energy established from officer records Corporate record (read 14 September 2026)
Elm Flats Solar SLF
County
Navarro
Technology
Solar, photovoltaic
Capacity
125.84 MW
Interconnecting entity
Orca Falls Solar, LLC
Point of interconnection
Tap 138kV 3472 BRIAR_CRK_8 – 3467 POWELL1_8
Status
SS Completed, FIS Started, IA
Projected completion
30 September 2027
Queue number
26INR0130
  • T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
  • T1Navarro County — Orca Falls Solar rezoning denied Feb 2026; road crossings approved Aug 2026 Commissioners Court (read 14 September 2026)
Elm Flats Storage SLF
County
Navarro
Technology
Other, battery
Capacity
Filed as 0 MW in the queue
Interconnecting entity
Orca Falls Solar, LLC
Point of interconnection
Tap 138kV 3472 BRIAR_CRK_8 – 3467 POWELL1_8
Status
SS Completed, FIS Started, IA
Projected completion
30 September 2027
Queue number
26INR0131
  • T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
  • T1Navarro County — Orca Falls Solar rezoning denied Feb 2026; road crossings approved Aug 2026 Commissioners Court (read 14 September 2026)
Glasgow Solar
County
Navarro
Technology
Solar, photovoltaic
Capacity
203.5 MW
Interconnecting entity
Glasgow Solar LLC
Developer
Belltown Power
Point of interconnection
Tap 345kV #2466 Big Onion - #68091 Navarro
Status
SS Completed, FIS Started, IA
Projected completion
16 March 2028
Queue number
24INR0206
  • T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
  • T1Belltown Power established from officer records Corporate record (read 14 September 2026)
Glasgow Storage
County
Navarro
Technology
Other, battery
Capacity
101 MW
Interconnecting entity
Glasgow Solar LLC
Developer
Belltown Power
Point of interconnection
Tap 345kV #2466 Big Onion - #68091 Navarro
Status
SS Completed, FIS Started, IA
Projected completion
16 March 2028
Queue number
24INR0207
  • T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
  • T1Belltown Power established from officer records Corporate record (read 14 September 2026)
Goodalta Solar
County
Navarro
Technology
Solar, photovoltaic
Capacity
221.36 MW
Interconnecting entity
GoodAlta Power Center LLC
Point of interconnection
tap 138kV 3127 Trinidad - 212 Winkler
Status
SS Completed, FIS Completed, No IA
Projected completion
20 September 2027
Queue number
23INR0171
  • T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
  • T1Navarro County — GoodAlta Power Center LLC tax abatement failed for want of a second, 2021 Commissioners Court (read 14 September 2026)
Hector Solar
County
Navarro
Technology
Solar, photovoltaic
Capacity
81.59 MW
Interconnecting entity
Hector Solar, LLC
Developer
Samsung C&T Renewables
Point of interconnection
Haney (213) - Hubbard_8 (3515) 138kV Line
Status
SS Completed, FIS Started, No IA
Projected completion
8 October 2028
Queue number
25INR0220
  • T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
  • T1Samsung C&T Renewables established from officer records; absent from Navarro County records entirely Corporate record (read 14 September 2026)
Hector Storage
County
Navarro
Technology
Other, battery
Capacity
42.69 MW
Interconnecting entity
Hector Solar, LLC
Developer
Samsung C&T Renewables
Point of interconnection
Haney (213) - Hubbard_8 (3515) 138kV Line
Status
SS Completed, FIS Started, No IA
Projected completion
8 October 2028
Queue number
25INR0221
  • T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
  • T1Samsung C&T Renewables established from officer records; absent from Navarro County records entirely Corporate record (read 14 September 2026)
Kennedy Solar
County
Navarro
Technology
Solar, photovoltaic
Capacity
101.5 MW
Interconnecting entity
Kennedy Bypass Solar LLC
Point of interconnection
Tap 345kV 68040 Kopprl Capacitor Yard - 68091 Navarro
Status
SS Completed, FIS Started, No IA
Projected completion
31 December 2028
Queue number
24INR0256

Kennedy Bypass Solar LLC has no Texas corporate registration. The project exists as a queue position and nothing else on record.

  • T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
  • T1Kennedy Bypass Solar LLC has no Texas corporate registration of any kind — checked against franchise tax, Secretary of State, EIA, TCEQ, Navarro County minutes, Chapter 312 and the Comptroller JETI registry. The project exists only as a queue position. Documented negative (read 14 September 2026)
Kennedy Storage
County
Navarro
Technology
Other, battery
Capacity
25.3 MW
Interconnecting entity
Kennedy Bypass Solar LLC
Point of interconnection
Tap 345kV 68040 Kopprl Capacitor Yard - 68091 Navarro
Status
SS Completed, FIS Started, No IA
Projected completion
31 December 2028
Queue number
24INR0391

Kennedy Bypass Solar LLC has no Texas corporate registration. The project exists as a queue position and nothing else on record.

  • T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
  • T1Kennedy Bypass Solar LLC has no Texas corporate registration of any kind — checked against franchise tax, Secretary of State, EIA, TCEQ, Navarro County minutes, Chapter 312 and the Comptroller JETI registry. The project exists only as a queue position. Documented negative (read 14 September 2026)
Main Horn Solar
County
Navarro
Technology
Solar, photovoltaic
Capacity
100.43 MW — EIA Form 860M gives 100 MW; the ERCOT queue gives 100.43 MW.
Interconnecting entity
Main Horn Solar LLC
Developer
OCI Energy
Point of interconnection
3387 Revolution 138 KV
Status
SS Completed, FIS Started, No IA
Projected completion
17 September 2029
Queue number
28INR0467
  • T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
  • T1EIA Form 860M, July 2026 — Plant 69636, Main Horn Solar, 100 MW, planned EIA Form 860M (read 14 September 2026)
Oak Valley Solar
County
Navarro
Technology
Solar, photovoltaic
Capacity
251.3 MW
Interconnecting entity
Oak Valley Solar LLC
Developer
Alpin Solar SA, Brașov, Romania (via Alpin Holding LLC, Canyon, Texas)
Point of interconnection
68091 (Navarro) (345)
Status
SS Completed, FIS Started, No IA
Projected completion
28 September 2029
Queue number
28INR0335
  • T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
  • T1Alpin Holding LLC of Canyon, Texas, parent Alpin Solar SA of Brașov, Romania, from officer records. Appears in no county record, no federal inventory and no trade press. Corporate record (read 14 September 2026)
Pisgah Ridge Solar 2
County
Navarro
Technology
Solar, photovoltaic
Capacity
101.89 MW
Interconnecting entity
Pisgah Ridge Solar 2, LLC
Developer
Duke Energy
Point of interconnection
Tap 345kV 68091 Navarro - 46020 Limestone
Status
SS Completed, FIS Started, No IA
Projected completion
31 March 2029
Queue number
24INR0086
  • T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
  • T1Navarro County Reinvestment Zone 20-102, Pisgah Ridge Solar, 3,688 acres, 200 MW minimum Commissioners Court (read 14 September 2026)
Ponferrada Solar
County
Navarro
Technology
Solar, photovoltaic
Capacity
148.87 MW
Interconnecting entity
Karol Solar VI
Developer
Solea Power Corp. (Houston and Madrid)
Point of interconnection
Tap 138 KV 3456 CORSWEST1_8 - 3457 CORS_MOBT_8
Status
SS Completed, FIS Started, No IA
Projected completion
6 April 2029
Queue number
28INR0182
  • T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
  • T1Karol Solar VI, parent Solea Power Corp. of Houston and Madrid, from officer records Corporate record (read 14 September 2026)
Santa Monica Solar
County
Navarro
Technology
Solar, photovoltaic
Capacity
105.85 MW
Interconnecting entity
Karol Solar IV
Developer
Solea Power Corp. (Houston and Madrid)
Point of interconnection
Tap 345 KV 68091 NAVARRO - 3381 BIGBRNW_5 Ckt 2
Status
SS Completed, FIS Completed, No IA
Projected completion
20 September 2028
Queue number
26INR0228
  • T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
  • T1Karol Solar IV, parent Solea Power Corp. of Houston and Madrid, from officer records Corporate record (read 14 September 2026)
TORMES SOLAR
County
Navarro
Technology
Solar, photovoltaic
Capacity
356.6 MW — Matrix Renewables states 457 MWdc; the ERCOT queue gives 356.6 MW. These are direct-current and alternating-current nameplate figures for the same project, not a contradiction.
Interconnecting entity
BDPU SOLAR TORMES LLC
Developer
Matrix Renewables (TPG Rise Climate)
Point of interconnection
tap 345kV 1906 Venus - 68091 Navarro
Status
SS Completed, FIS Completed, IA
Projected completion
31 March 2027
Queue number
22INR0437
  • T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
  • T2Matrix Renewables press release and project page, 28 May 2026 — groundbreaking 19 May 2026, 457 MWdc, approximately $750M, EPC contractor SOLV Energy, site about two miles southeast of Barry, west of Corsicana Developer publication (read 14 September 2026)
Wensowitch Solar
County
Navarro
Technology
Solar, photovoltaic
Capacity
146.08 MW — EIA Form 860M gives 145.6 MW; the ERCOT queue gives 146.08 MW.
Interconnecting entity
Greenalia Solar Power Wensowitch LLC
Developer
Greenalia S.A. (Spain)
Point of interconnection
Tapping 138 kV line Telico (192) to Montfort Switch (3454)
Status
SS Completed, FIS Completed, No IA
Projected completion
18 September 2028
Queue number
24INR0205
  • T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
  • T1EIA Form 860M, July 2026 — Plant 67567, Wensowitch Solar Park, 145.6 MW EIA Form 860M (read 14 September 2026)
Wildflower Storage
County
Navarro
Technology
Other, battery
Capacity
359.1 MW
Interconnecting entity
Wildflower Storage LLC
Developer
Matrix Renewables (TPG Rise Climate)
Point of interconnection
Drane switch #3295
Status
SS Completed, FIS Started, No IA
Projected completion
30 September 2028
Queue number
28INR0292
  • T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
  • T1Matrix Renewables (TPG Rise Climate) established from officer records Corporate record (read 14 September 2026)
Yellow Cat Wind
County
Navarro
Technology
Wind, wind turbine
Capacity
262 MW — RWE states 270 MW; the ERCOT queue gives 262 MW.
Interconnecting entity
Yellow Cat Wind LLC
Developer
RWE
Point of interconnection
Tap 345kV 1906 Venus - 68091 Navarro
Status
SS Completed, FIS Completed, IA
Projected completion
5 March 2027
Queue number
25INR0018

RWE's own project page places part of this project in Ellis County, which is outside the two counties this page covers.

  • T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
  • T2RWE project page — developer confirmed, “over 67,250 homes” powered, 30-year landowner lease framing, and a stated capacity of 270 MW against the queue's 262 MW. The same page places the project in Navarro, Ellis and Hill counties. Developer publication (read 14 September 2026)

Hill County

Generation projects holding an active position in the ERCOT interconnection queue.

Aquilla Lake 3 Wind
County
Hill
Technology
Wind, wind turbine
Capacity
297.4 MW
Interconnecting entity
Aquilla Lake 3 Wind
Developer
NextEra Energy Resources (via Hubbard Wind II, LLC)
Point of interconnection
tap 345 kV 68040 Kopperl to 68091 Navarro
Status
SS Completed, FIS Completed, IA
Projected completion
20 November 2026
Queue number
22INR0499
  • T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
  • T1PUC Docket 57836 — Lone Star Transmission CCN amendment filed 11 Apr 2025 for the Bullock Station to Aquilla Lake III 345-kV line, naming Hubbard Wind II, LLC PUCT filing (read 14 September 2026)
Blue Skies BESS
County
Hill
Technology
Other, battery
Capacity
306.26 MW
Interconnecting entity
ACTX BESS Project LLC
Developer
Primergy Solar (Quinbrook Infrastructure Partners)
Point of interconnection
68090 SAM SW 345kV
Status
SS Completed, FIS Started, IA
Projected completion
1 April 2028
Queue number
25INR0046

Primergy's franchise mailing address has moved to Scottsdale, Arizona. The parent should be re-checked before this row is relied on.

  • T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
  • T1Primergy Solar (Quinbrook Infrastructure Partners) established from officer records Corporate record (read 14 September 2026)
Compadre Solar
County
Hill
Technology
Solar, photovoltaic
Capacity
405.7 MW
Interconnecting entity
Hill Solar I, LLC
Developer
OCI Energy
Point of interconnection
tap 345kV 68090 Sam Switch - 1907 Venus
Status
SS Completed, FIS Completed, IA
Projected completion
31 July 2026
Queue number
24INR0023
  • T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
  • T1Hill County road use agreement with Hill Solar I, LLC, 25 Apr 2023 Commissioners Court (read 14 September 2026)
Compadre Solar II
County
Hill
Technology
Solar, photovoltaic
Capacity
201.4 MW
Interconnecting entity
Hill Solar II, LLC
Developer
OCI Energy
Point of interconnection
Tap 345kV 68090 Sam Switch – 3389 Fort Smith
Status
SS Completed, FIS Completed, IA
Projected completion
1 October 2026
Queue number
25INR0166
  • T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
  • T1Hill County road use agreement with Hill Solar II, 27 Dec 2023 Commissioners Court (read 14 September 2026)
Edens Solar
County
Hill
Technology
Solar, photovoltaic
Capacity
70.75 MW
Interconnecting entity
Hill PV, LLC
Developer
OCI Energy
Point of interconnection
Tap 69kV 3532 Itasca - 3523 Hillsboro
Status
SS Completed, FIS Started, No IA
Projected completion
9 April 2028
Queue number
26INR0313
  • T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
  • T1Hill County Reinvestment Zone 20 for Hill PV, LLC, 22 Oct 2024, and tax abatement 10 Dec 2024 Commissioners Court (read 14 September 2026)
High Noon Solar
County
Hill
Technology
Solar, photovoltaic
Capacity
182 MW
Interconnecting entity
High Noon Solar Project, LLC
Developer
Enel Green Power North America
Point of interconnection
Tap 138kV 445 Yates - 444 Covington
Status
SS Completed, FIS Started, IA
Projected completion
9 May 2028
Queue number
24INR0124
  • T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
  • T1Enel Green Power North America established from officer records Corporate record (read 14 September 2026)
High Noon Storage
County
Hill
Technology
Other, battery
Capacity
94 MW
Interconnecting entity
High Noon Solar Project, LLC
Developer
Enel Green Power North America
Point of interconnection
Tap 138kV 445 Yates - 444 Covington
Status
SS Completed, FIS Started, IA
Projected completion
9 May 2028
Queue number
24INR0126
  • T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
  • T1Enel Green Power North America established from officer records Corporate record (read 14 September 2026)
NRG Prairie Energy Center
County
Hill
Technology
Gas, combined cycle
Capacity
1,253 MW
Interconnecting entity
NRG Prairie Energy Center LLC
Point of interconnection
Tap #1907 Venus Switch – #3389 Fort Smith Switch 345 kV
Status
SS Completed, FIS Started, No IA
Projected completion
31 December 2030
Queue number
29INR0158

Recorded on 13 Sep 2026 as a project appearing on no tracker. It is in the ERCOT generation queue, and this page corrects that.

  • T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
  • T1TCEQ air permit application 183570 / PSDTX1706 / GHGPSDTX272, received 31 Mar 2026, expedited — power generation at CR 4419 / FM 66 southeast of Grandview; filed with the Hill County Judge on the county projects page TCEQ (read 14 September 2026)
OCI Cobb Creek ESS
County
Hill
Technology
Other, battery
Capacity
201.6 MW
Interconnecting entity
Hillsboro Solar Project LLC
Developer
OCI Energy
Point of interconnection
tap 345kV 1907 Venus - 68090 Sam Sw
Status
SS Completed, FIS Completed, IA
Projected completion
31 December 2028
Queue number
25INR0233
  • T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
  • T1Hill County Reinvestment Zone 012, OCI Hillsboro Solar, with assignee Hillsboro BESS Project LLC Commissioners Court (read 14 September 2026)
OCI Cobb Creek Solar
County
Hill
Technology
Solar, photovoltaic
Capacity
203.1 MW
Interconnecting entity
Hillsboro Solar Project LLC
Developer
OCI Energy
Point of interconnection
tap 345kV 1907 Venus - 68090 Sam Sw
Status
SS Completed, FIS Completed, IA
Projected completion
31 December 2027
Queue number
25INR0229
  • T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
  • T1Hill County Reinvestment Zone 012, OCI Hillsboro Solar Commissioners Court (read 14 September 2026)
Payne Battlecreek
County
Hill
Technology
Solar, photovoltaic
Capacity
84.99 MW — The Hill County record gives 83.6 MWac; the ERCOT queue gives 84.99 MW.
Interconnecting entity
Gransolar Texas Ten, LLC
Developer
Gransolar
Point of interconnection
tap 138kV 213 Haney - 3515 Hubbard
Status
SS Completed, FIS Started, IA
Projected completion
25 August 2027
Queue number
24INR0106
  • T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
  • T1Hill County Reinvestment Zone 009, Gransolar Texas Ten, 83.6 MWac as stated in the county record Commissioners Court (read 14 September 2026)
Seven Angels Energy Storage I
County
Hill
Technology
Other, battery
Capacity
514 MW
Interconnecting entity
Seven Angels Infrastructure LLC
Developer
Polaris Infrastructure Development LLC, originated by Macro Grid Solutions LLC (both Denver)
Point of interconnection
68090 Sam Switch Bus 345kV
Status
SS Completed, FIS Started, No IA
Projected completion
31 December 2028
Queue number
28INR0472
  • T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
  • T1Polaris Infrastructure Development LLC, originated by Macro Grid Solutions LLC, both of Denver, from officer records Corporate record (read 14 September 2026)
Seven Angels Energy Storage II
County
Hill
Technology
Other, battery
Capacity
514 MW
Interconnecting entity
Seven Angels Infrastructure LLC
Developer
Polaris Infrastructure Development LLC, originated by Macro Grid Solutions LLC (both Denver)
Point of interconnection
68090 Sam Switch Bus 345kV
Status
SS Completed, FIS Started, No IA
Projected completion
31 December 2028
Queue number
28INR0473
  • T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
  • T1Polaris Infrastructure Development LLC, originated by Macro Grid Solutions LLC, both of Denver, from officer records Corporate record (read 14 September 2026)
Three W Solar
County
Hill
Technology
Solar, photovoltaic
Capacity
110.89 MW
Interconnecting entity
Three W Solar LLC
Point of interconnection
tap 138kV 3522 Hillboro1_8 - 237 Blanton CKT 1
Status
SS Completed, FIS Completed, IA
Projected completion
4 September 2026
Queue number
25INR0055
  • T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
  • T1Hill County Reinvestment Zone 013, Three W Solar, with four named landowners publicly noticed (Westmoreland ×2, Swann, Williams) Commissioners Court (read 14 September 2026)
Vial BESS
County
Hill
Technology
Other, battery
Capacity
135.18 MW — The Hill County record gives 135.12 MWac; the ERCOT queue gives 135.18 MW.
Interconnecting entity
Gransolar Texas Eleven LLC
Developer
Gransolar
Point of interconnection
Chatt(234) - Pecan Street (3352) 138kV
Status
SS Completed, FIS Completed, IA
Projected completion
15 September 2027
Queue number
25INR0122
  • T1GIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (read 14 September 2026)
  • T1Hill County Reinvestment Zone 014, Gransolar Texas Eleven, 135.12 MWac BESS as stated in the county record Commissioners Court (read 14 September 2026)
14 further projects are on record in these two counties and not listed here. Each rests on a single record, and this page does not publish a figure that only one source states. They are held in the page's own data file.

6 queue positions in these counties are carried by ERCOT as inactive. An inactive position is not a project and is not listed here.

Queue data: ERCOT GIS Report for August 2026, posted 1 September 2026, read 14 September 2026. Second sources are named against each project. Where two records give different figures for the same project, both are shown with their sources and neither is picked. ERCOT publishes the report for planning purposes only, states that its data comes from the interconnecting entities and transmission service providers themselves, and cautions that it may contain errors or be out of date depending on when it was entered. Compiled by Blackland TX.

The towns and what is kept → · The map of towns and places →