Vial BESS

No public record places this project more closely than Hill County, which is outlined.
County
Hill
Technology
Battery storage
Capacity
135.18 MW — The Hill County record gives 135.12 MWac; the ERCOT queue gives 135.18 MW.
Interconnecting entity
Gransolar Texas Eleven LLC
Developer
Gransolar
Point of interconnection
Chatt(234) - Pecan Street (3352) 138kV
Status
SS Completed, FIS Completed, IA
Projected completion
15 September 2027
Queue number
25INR0122
  • Public recordGIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (checked 14 September 2026)
  • Public recordHill County Reinvestment Zone 014, Gransolar Texas Eleven, 135.12 MWac BESS as stated in the county record Commissioners Court (checked 14 September 2026)

ERCOT's abbreviations: SS, the security screening study; FIS, the full interconnection study; IA, the interconnection agreement. How this page is sourced →

Queue data: ERCOT GIS Report, August 2026 (posted 1 September 2026, read 30 September 2026). ERCOT publishes it for planning only; its data comes from the project companies and may contain errors. Compiled by Blackland TX. Corrections: [email protected].