BLACKLAND TXthe six towns →

← Energy and data-center projects

Blue Skies BESS

Sam Switch
It connects to the grid at Sam Switch (marked). The project's own site is not public; Hill County is outlined.
County
Hill
Technology
Battery storage
Capacity
306.26 MW
Interconnecting entity
ACTX BESS Project LLC
Developer
Primergy Solar (Quinbrook Infrastructure Partners)
Point of interconnection
68090 SAM SW 345kV
Status
SS Completed, FIS Started, IA
Projected completion
1 April 2028
Queue number
25INR0046

Primergy's franchise mailing address is now in Scottsdale, Arizona.

  • Public recordGIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (checked 14 September 2026)
  • Public recordPrimergy Solar (Quinbrook Infrastructure Partners) established from officer records Corporate record (checked 14 September 2026)

ERCOT's abbreviations: SS, the security screening study; FIS, the full interconnection study; IA, the interconnection agreement. How this page is sourced →

Queue data: ERCOT GIS Report, August 2026 (posted 1 September 2026, read 30 September 2026). ERCOT publishes it for planning only; its data comes from the project companies and may contain errors. Compiled by Blackland TX. Corrections: [email protected].