Wensowitch Solar
- County
- Navarro
- Technology
- Solar
- Capacity
- 146.08 MW
- Interconnecting entity
- Greenalia Solar Power Wensowitch LLC
- Developer
- Greenalia S.A. (Spain)
- Point of interconnection
- Tapping 138 kV line Telico (192) to Montfort Switch (3454)
- Status
- SS Completed, FIS Completed, No IA
- Projected completion
- 18 September 2028
- Queue number
- 24INR0205
- Public recordGIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (checked 14 September 2026)
- Public recordEIA Form 860M, July 2026 — Plant 67567, Wensowitch Solar Park, 145.6 MW EIA Form 860M (checked 14 September 2026)
ERCOT's abbreviations: SS, the security screening study; FIS, the full interconnection study; IA, the interconnection agreement. How this page is sourced →
Queue data: ERCOT GIS Report, August 2026 (posted 1 September 2026, read 30 September 2026). ERCOT publishes it for planning only; its data comes from the project companies and may contain errors. Compiled by Blackland TX. Corrections: [email protected].