Yellow Cat Wind
- County
- Navarro
- Technology
- Wind
- Capacity
- 262 MW
- Interconnecting entity
- Yellow Cat Wind LLC
- Developer
- RWE
- Point of interconnection
- Tap 345kV 1906 Venus - 68091 Navarro
- Status
- SS Completed, FIS Completed, IA
- Projected completion
- 5 March 2027
- Queue number
- 25INR0018
RWE's own project page places part of this project in Ellis County, which is outside the two counties this page covers.
The project's operations and maintenance building is registered with the state at 15822 W State Highway 22, Frost, in Navarro County, with construction scheduled for June to December 2026. That places the building, not the turbines.
- Public recordGIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (checked 14 September 2026)
- Company claimRWE project page — developer confirmed, “over 67,250 homes” powered, 30-year landowner lease framing, and a stated capacity of 270 MW against the queue's 262 MW. The same page places the project in Navarro, Ellis and Hill counties. Developer publication (checked 14 September 2026)
- Public recordTexas Department of Licensing and Regulation, Architectural Barriers project TABS2026021052, registered 22 May 2026: “RWE Clean Energy Yellow CAT Wind Farm”, a 4,800 sq ft operations and maintenance building at 15822 W State Highway 22, Frost, TX 76641, Navarro County; construction scheduled 1 Jun to 15 Dec 2026; status Review Complete. TDLR filing (checked 16 September 2026)
ERCOT's abbreviations: SS, the security screening study; FIS, the full interconnection study; IA, the interconnection agreement. How this page is sourced →
Queue data: ERCOT GIS Report, August 2026 (posted 1 September 2026, read 30 September 2026). ERCOT publishes it for planning only; its data comes from the project companies and may contain errors. Compiled by Blackland TX. Corrections: [email protected].