Glasgow Solar

Navarro Switch
It taps a transmission line that runs to Navarro Switch (marked). Where on the line is not public, and the line is not drawn. Navarro County is outlined.
County
Navarro
Technology
Solar
Capacity
203.5 MW
Interconnecting entity
Glasgow Solar LLC
Developer
Belltown Power
Point of interconnection
Tap 345kV #2466 Big Onion - #68091 Navarro
Status
SS Completed, FIS Started, IA
Projected completion
16 March 2028
Queue number
24INR0206
  • Public recordGIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (checked 14 September 2026)
  • Public recordBelltown Power established from officer records Corporate record (checked 14 September 2026)

ERCOT's abbreviations: SS, the security screening study; FIS, the full interconnection study; IA, the interconnection agreement. How this page is sourced →

Queue data: ERCOT GIS Report, August 2026 (posted 1 September 2026, read 30 September 2026). ERCOT publishes it for planning only; its data comes from the project companies and may contain errors. Compiled by Blackland TX. Corrections: [email protected].