Payne Battlecreek
- County
- Hill
- Technology
- Solar
- Capacity
- 84.99 MW
- Interconnecting entity
- Gransolar Texas Ten, LLC
- Developer
- Gransolar
- Point of interconnection
- tap 138kV 213 Haney - 3515 Hubbard
- Status
- SS Completed, FIS Started, IA
- Projected completion
- 25 August 2027
- Queue number
- 24INR0106
- Public recordGIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (checked 14 September 2026)
- Public recordHill County Reinvestment Zone 009, Gransolar Texas Ten, 83.6 MWac as stated in the county record Commissioners Court (checked 14 September 2026)
ERCOT's abbreviations: SS, the security screening study; FIS, the full interconnection study; IA, the interconnection agreement. How this page is sourced →
Queue data: ERCOT GIS Report, August 2026 (posted 1 September 2026, read 30 September 2026). ERCOT publishes it for planning only; its data comes from the project companies and may contain errors. Compiled by Blackland TX. Corrections: [email protected].