Tormes Solar

Location from Navarro Central Appraisal District (14 September 2026). The circle is the margin: within about 5 miles.
County
Navarro
Technology
Solar
Capacity
356.6 MW — Matrix Renewables states 457 MWdc; the ERCOT queue gives 356.6 MW. These are direct-current and alternating-current nameplate figures for the same project, not a contradiction.
Interconnecting entity
BDPU SOLAR TORMES LLC
Developer
Matrix Renewables (TPG Rise Climate)
Point of interconnection
tap 345kV 1906 Venus - 68091 Navarro
Status
SS Completed, FIS Completed, IA
Projected completion
31 March 2027
Queue number
22INR0437

The Navarro County Appraisal District parcel tied to this project (BDPU Solar Tormes LLC, 21.60 acres) sits about 2.9 miles south-southwest of Barry. Matrix Renewables' own release places the project about two miles southeast of Barry.

  • Public recordGIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (checked 14 September 2026)
  • Company claimMatrix Renewables press release and project page, 28 May 2026 — groundbreaking 19 May 2026, 457 MWdc, approximately $750M, EPC contractor SOLV Energy, site about two miles southeast of Barry, west of Corsicana Developer publication (checked 14 September 2026)

ERCOT's abbreviations: SS, the security screening study; FIS, the full interconnection study; IA, the interconnection agreement. How this page is sourced →

Queue data: ERCOT GIS Report, August 2026 (posted 1 September 2026, read 30 September 2026). ERCOT publishes it for planning only; its data comes from the project companies and may contain errors. Compiled by Blackland TX. Corrections: [email protected].