- County
- Navarro
- Technology
- Solar
- Capacity
- 81.59 MW
- Interconnecting entity
- Hector Solar, LLC
- Developer
- Samsung C&T Renewables
- Point of interconnection
- Haney (213) - Hubbard_8 (3515) 138kV Line
- Status
- SS Completed, FIS Started, No IA
- Projected completion
- 8 October 2028
- Queue number
- 25INR0220
- Public recordGIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (checked 14 September 2026)
- Public recordSamsung C&T Renewables established from officer records; absent from Navarro County records entirely Corporate record (checked 14 September 2026)
ERCOT's abbreviations: SS, the security screening study; FIS, the full interconnection study; IA, the interconnection agreement. How this page is sourced →
Queue data: ERCOT GIS Report, August 2026 (posted 1 September 2026, read 30 September 2026). ERCOT publishes it for planning only; its data comes from the project companies and may contain errors. Compiled by Blackland TX. Corrections: [email protected].