Hector Solar

No public record places this project more closely than Navarro County, which is outlined.
County
Navarro
Technology
Solar
Capacity
81.59 MW
Interconnecting entity
Hector Solar, LLC
Developer
Samsung C&T Renewables
Point of interconnection
Haney (213) - Hubbard_8 (3515) 138kV Line
Status
SS Completed, FIS Started, No IA
Projected completion
8 October 2028
Queue number
25INR0220
  • Public recordGIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (checked 14 September 2026)
  • Public recordSamsung C&T Renewables established from officer records; absent from Navarro County records entirely Corporate record (checked 14 September 2026)

ERCOT's abbreviations: SS, the security screening study; FIS, the full interconnection study; IA, the interconnection agreement. How this page is sourced →

Queue data: ERCOT GIS Report, August 2026 (posted 1 September 2026, read 30 September 2026). ERCOT publishes it for planning only; its data comes from the project companies and may contain errors. Compiled by Blackland TX. Corrections: [email protected].