Pisgah Ridge Solar 2

Location from EIA Form 860/860M plant file (14 September 2026). Accurate to within about 0.6 miles.
County
Navarro
Technology
Solar
Capacity
101.89 MW
Interconnecting entity
Pisgah Ridge Solar 2, LLC
Developer
Duke Energy
Point of interconnection
Tap 345kV 68091 Navarro - 46020 Limestone
Status
SS Completed, FIS Started, No IA
Projected completion
31 March 2029
Queue number
24INR0086
  • Public recordGIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (checked 14 September 2026)
  • Public recordNavarro County Reinvestment Zone 20-102, Pisgah Ridge Solar, 3,688 acres, 200 MW minimum Commissioners Court (checked 14 September 2026)

ERCOT's abbreviations: SS, the security screening study; FIS, the full interconnection study; IA, the interconnection agreement. How this page is sourced →

Queue data: ERCOT GIS Report, August 2026 (posted 1 September 2026, read 30 September 2026). ERCOT publishes it for planning only; its data comes from the project companies and may contain errors. Compiled by Blackland TX. Corrections: [email protected].