Pisgah Ridge Solar 2
- County
- Navarro
- Technology
- Solar
- Capacity
- 101.89 MW
- Interconnecting entity
- Pisgah Ridge Solar 2, LLC
- Developer
- Duke Energy
- Point of interconnection
- Tap 345kV 68091 Navarro - 46020 Limestone
- Status
- SS Completed, FIS Started, No IA
- Projected completion
- 31 March 2029
- Queue number
- 24INR0086
- Public recordGIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (checked 14 September 2026)
- Public recordNavarro County Reinvestment Zone 20-102, Pisgah Ridge Solar, 3,688 acres, 200 MW minimum Commissioners Court (checked 14 September 2026)
ERCOT's abbreviations: SS, the security screening study; FIS, the full interconnection study; IA, the interconnection agreement. How this page is sourced →
Queue data: ERCOT GIS Report, August 2026 (posted 1 September 2026, read 30 September 2026). ERCOT publishes it for planning only; its data comes from the project companies and may contain errors. Compiled by Blackland TX. Corrections: [email protected].