Goodalta Solar

No public record places this project more closely than Navarro County, which is outlined.
County
Navarro
Technology
Solar
Capacity
221.36 MW
Interconnecting entity
GoodAlta Power Center LLC
Point of interconnection
tap 138kV 3127 Trinidad - 212 Winkler
Status
SS Completed, FIS Completed, No IA
Projected completion
20 September 2027
Queue number
23INR0171
  • Public recordGIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (checked 14 September 2026)
  • Public recordNavarro County — GoodAlta Power Center LLC tax abatement failed for want of a second, 2021 Commissioners Court (checked 14 September 2026)

ERCOT's abbreviations: SS, the security screening study; FIS, the full interconnection study; IA, the interconnection agreement. How this page is sourced →

Queue data: ERCOT GIS Report, August 2026 (posted 1 September 2026, read 30 September 2026). ERCOT publishes it for planning only; its data comes from the project companies and may contain errors. Compiled by Blackland TX. Corrections: [email protected].