← Energy and data-center projects
Oak Valley Solar
- County
- Navarro
- Technology
- Solar
- Capacity
- 251.3 MW
- Interconnecting entity
- Oak Valley Solar LLC
- Developer
- Alpin Solar SA, Brașov, Romania (via Alpin Holding LLC, Canyon, Texas)
- Point of interconnection
- 68091 (Navarro) (345)
- Status
- SS Completed, FIS Started, No IA
- Projected completion
- 28 September 2029
- Queue number
- 28INR0335
- Public recordGIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (checked 14 September 2026)
- Public recordAlpin Holding LLC of Canyon, Texas, parent Alpin Solar SA of Brașov, Romania, from officer records. Appears in no county record, no federal inventory and no trade press. Corporate record (checked 14 September 2026)
ERCOT's abbreviations: SS, the security screening study; FIS, the full interconnection study; IA, the interconnection agreement. How this page is sourced →
Queue data: ERCOT GIS Report, August 2026 (posted 1 September 2026, read 30 September 2026). ERCOT publishes it for planning only; its data comes from the project companies and may contain errors. Compiled by Blackland TX. Corrections: [email protected].