Aquilla Lake 3 Wind
- County
- Hill
- Technology
- Wind
- Capacity
- 297.4 MW
- Interconnecting entity
- Aquilla Lake 3 Wind
- Developer
- NextEra Energy Resources (via Hubbard Wind II, LLC)
- Point of interconnection
- tap 345 kV 68040 Kopperl to 68091 Navarro
- Status
- SS Completed, FIS Completed, IA
- Projected completion
- 20 November 2026
- Queue number
- 22INR0499
- Public recordGIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (checked 14 September 2026)
- Public recordPUC Docket 57836 — Lone Star Transmission CCN amendment filed 11 Apr 2025 for the Bullock Station to Aquilla Lake III 345-kV line, naming Hubbard Wind II, LLC PUCT filing (checked 14 September 2026)
ERCOT's abbreviations: SS, the security screening study; FIS, the full interconnection study; IA, the interconnection agreement. How this page is sourced →
Queue data: ERCOT GIS Report, August 2026 (posted 1 September 2026, read 30 September 2026). ERCOT publishes it for planning only; its data comes from the project companies and may contain errors. Compiled by Blackland TX. Corrections: [email protected].