Aquilla Lake 3 Wind

Navarro Switch
It taps a transmission line that runs to Navarro Switch (marked). Where on the line is not public, and the line is not drawn. Hill County is outlined.
County
Hill
Technology
Wind
Capacity
297.4 MW
Interconnecting entity
Aquilla Lake 3 Wind
Developer
NextEra Energy Resources (via Hubbard Wind II, LLC)
Point of interconnection
tap 345 kV 68040 Kopperl to 68091 Navarro
Status
SS Completed, FIS Completed, IA
Projected completion
20 November 2026
Queue number
22INR0499
  • Public recordGIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (checked 14 September 2026)
  • Public recordPUC Docket 57836 — Lone Star Transmission CCN amendment filed 11 Apr 2025 for the Bullock Station to Aquilla Lake III 345-kV line, naming Hubbard Wind II, LLC PUCT filing (checked 14 September 2026)

ERCOT's abbreviations: SS, the security screening study; FIS, the full interconnection study; IA, the interconnection agreement. How this page is sourced →

Queue data: ERCOT GIS Report, August 2026 (posted 1 September 2026, read 30 September 2026). ERCOT publishes it for planning only; its data comes from the project companies and may contain errors. Compiled by Blackland TX. Corrections: [email protected].