← Energy and data-center projects
Ponferrada Solar
- County
- Navarro
- Technology
- Solar
- Capacity
- 148.87 MW
- Interconnecting entity
- Karol Solar VI
- Developer
- Solea Power Corp. (Houston and Madrid)
- Point of interconnection
- Tap 138 KV 3456 CORSWEST1_8 - 3457 CORS_MOBT_8
- Status
- SS Completed, FIS Started, No IA
- Projected completion
- 6 April 2029
- Queue number
- 28INR0182
- Public recordGIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (checked 14 September 2026)
- Public recordKarol Solar VI, parent Solea Power Corp. of Houston and Madrid, from officer records Corporate record (checked 14 September 2026)
ERCOT's abbreviations: SS, the security screening study; FIS, the full interconnection study; IA, the interconnection agreement. How this page is sourced →
Queue data: ERCOT GIS Report, August 2026 (posted 1 September 2026, read 30 September 2026). ERCOT publishes it for planning only; its data comes from the project companies and may contain errors. Compiled by Blackland TX. Corrections: [email protected].