High Noon Solar
- County
- Hill
- Technology
- Solar
- Capacity
- 182 MW
- Interconnecting entity
- High Noon Solar Project, LLC
- Developer
- Enel Green Power North America
- Point of interconnection
- Tap 138kV 445 Yates - 444 Covington
- Status
- SS Completed, FIS Started, IA
- Projected completion
- 9 May 2028
- Queue number
- 24INR0124
- Public recordGIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (checked 14 September 2026)
- Public recordEnel Green Power North America established from officer records Corporate record (checked 14 September 2026)
ERCOT's abbreviations: SS, the security screening study; FIS, the full interconnection study; IA, the interconnection agreement. How this page is sourced →
Queue data: ERCOT GIS Report, August 2026 (posted 1 September 2026, read 30 September 2026). ERCOT publishes it for planning only; its data comes from the project companies and may contain errors. Compiled by Blackland TX. Corrections: [email protected].