Santa Monica Solar

Navarro Switch
It taps a transmission line that runs to Navarro Switch (marked). Where on the line is not public, and the line is not drawn. Navarro County is outlined.
County
Navarro
Technology
Solar
Capacity
105.85 MW
Interconnecting entity
Karol Solar IV
Developer
Solea Power Corp. (Houston and Madrid)
Point of interconnection
Tap 345 KV 68091 NAVARRO - 3381 BIGBRNW_5 Ckt 2
Status
SS Completed, FIS Completed, No IA
Projected completion
20 September 2028
Queue number
26INR0228
  • Public recordGIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (checked 14 September 2026)
  • Public recordKarol Solar IV, parent Solea Power Corp. of Houston and Madrid, from officer records Corporate record (checked 14 September 2026)

ERCOT's abbreviations: SS, the security screening study; FIS, the full interconnection study; IA, the interconnection agreement. How this page is sourced →

Queue data: ERCOT GIS Report, August 2026 (posted 1 September 2026, read 30 September 2026). ERCOT publishes it for planning only; its data comes from the project companies and may contain errors. Compiled by Blackland TX. Corrections: [email protected].