← Energy and data-center projects
Riot Platforms Corsicana
- County
- Navarro
- Technology
- Bitcoin mining and data center load
- Capacity
- 400 MW operational
- Interconnecting entity
- Riot Corsicana, LLC
- Developer
- Riot Platforms, Inc.
- Status
- Operational
- In service
- Substation energized April 2024
No amendment for the announced expansion to approximately 1 GW appears in Navarro County minutes.
- Public recordRiot Platforms FY2025 Form 10-K, accession 0001104659-26-022322, and Q2 2026 Form 10-Q, accession 0001104659-26-093448 — 265.71 acres in the J. Taylor Survey Block 233 Abstract 11, substation energized April 2024, 400 MW operational at 31 Dec 2024 and still 400 MW at 30 Jun 2026, approximately 1 GW planned, Oncor delivery SEC filing (checked 14 September 2026)
- Public recordNavarro County tax abatement approved 3–2 on 15 Oct 2024, Reinvestment Zone 24-102, 50% for 10 years, $640M, 140 jobs; the document states 920 MW of demand. An earlier attempt died for want of a second on 11 Mar 2024. Commissioners Court (checked 14 September 2026)
ERCOT's abbreviations: SS, the security screening study; FIS, the full interconnection study; IA, the interconnection agreement. How this page is sourced →
Queue data: ERCOT GIS Report, August 2026 (posted 1 September 2026, read 30 September 2026). ERCOT publishes it for planning only; its data comes from the project companies and may contain errors. Compiled by Blackland TX. Corrections: [email protected].