Edens Solar
- County
- Hill
- Technology
- Solar
- Capacity
- 70.75 MW
- Interconnecting entity
- Hill PV, LLC
- Developer
- OCI Energy
- Point of interconnection
- Tap 69kV 3532 Itasca - 3523 Hillsboro
- Status
- SS Completed, FIS Started, No IA
- Projected completion
- 9 April 2028
- Queue number
- 26INR0313
- Public recordGIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (checked 14 September 2026)
- Public recordHill County Reinvestment Zone 20 for Hill PV, LLC, 22 Oct 2024, and tax abatement 10 Dec 2024 Commissioners Court (checked 14 September 2026)
ERCOT's abbreviations: SS, the security screening study; FIS, the full interconnection study; IA, the interconnection agreement. How this page is sourced →
Queue data: ERCOT GIS Report, August 2026 (posted 1 September 2026, read 30 September 2026). ERCOT publishes it for planning only; its data comes from the project companies and may contain errors. Compiled by Blackland TX. Corrections: [email protected].