Kennedy Solar
- County
- Navarro
- Technology
- Solar
- Capacity
- 101.5 MW
- Interconnecting entity
- Kennedy Bypass Solar LLC
- Point of interconnection
- Tap 345kV 68040 Kopprl Capacitor Yard - 68091 Navarro
- Status
- SS Completed, FIS Started, No IA
- Projected completion
- 31 December 2028
- Queue number
- 24INR0256
Kennedy Bypass Solar LLC has no Texas corporate registration. The project exists as a queue position and nothing else on record.
- Public recordGIS Report for August 2026, posted 1 September 2026, sheet “Project Details – Large Gen” ERCOT GIS Report (checked 14 September 2026)
- Public recordKennedy Bypass Solar LLC has no Texas corporate registration of any kind — checked against franchise tax, Secretary of State, EIA, TCEQ, Navarro County minutes, Chapter 312 and the Comptroller JETI registry. The project exists only as a queue position. No filing found (checked 14 September 2026)
ERCOT's abbreviations: SS, the security screening study; FIS, the full interconnection study; IA, the interconnection agreement. How this page is sourced →
Queue data: ERCOT GIS Report, August 2026 (posted 1 September 2026, read 30 September 2026). ERCOT publishes it for planning only; its data comes from the project companies and may contain errors. Compiled by Blackland TX. Corrections: [email protected].